1. Demolish wall in entryway foyer. **Tore off drywall 6/19/09 Take out framing?
2. Complete all other demolition (master bath vanity, door frames?) **Took out master vanity 6/19/09.
3. Start cleaning concrete slab with mechanical buffer, stripper, Tri Sodium Phosphate. **Done
4. Spot clean floors for whatever doesn't come up with buffer. **Done.
4. Complete kitchen design (cabinets, etc.) **On second iteration - nearly done
5. Materials selection/purchase for kitchen.
6. Get contractor started in kitchen (cabinet construction, counter top placement, etc.)
7. Paint/Stain/Install cabinet doors and install new handles.
8. Have drywall contractor do patches and make home "Paint Ready"
9. Stain floors (except kitchen & guest bath)
10. Master Bathroom updates (counter top, sink, sink/tub/shower faucets, install toilet)
11. Guest bathroom demo
12. Stain floors in guest bath and kitchen
14. Guest bathroom updates (vanity, counter top, replace toilet, sink/tub/shower faucets)
15. Salvage/Locate/Install Baseboards
16. Interior Paint.
17. Install appliances
18. Move in.
19. Energy Audit.